| Name of Road : | Constrn. | Chhingchhip- Hualtu Road | ||||||||
| (FP) | Date of commencent 18.1.2014 | |||||||||
| Package No : | MZ 08-02-7-II(1) | |||||||||
| Length of Road : | 24.04 | Phase - VII-Pt II | Period of completetion 24 month | |||||||
| Agreement Amount : | 125955771 | Amount in lakhs | ||||||||
| Item of Works |
Unit | As per Aggrement | Progress upto the end of last month |
Progress during the month | Cummulative Progress | Remarks | ||||
| Phy | Fin | Phy | Fin | Phy | Fin | Phy | Fin | |||
| Pavement works | ||||||||||
| Repairs of Damages coused by Rain/ spillage of Water | Km | 20.250 | 3.63 | 25.250 | 0.00 | |||||
| Constr.of GSB | Km | 20.250 | 303.31 | 11.000 | 0.00 | |||||
| Cell Filled Concrete | Km | 20.250 | 757.67 | 0.000 | 0.00 | |||||
| Earthern Shoulder | Km | 1126.800 | 36.09 | 0.000 | 0.00 | |||||
| Premix carpet | Km | |||||||||
| Seal coat | Km | |||||||||
| Cell Fill | Km | |||||||||
| Earthern Shoulder | Cum | |||||||||
| Proctection works | ||||||||||
| R/W | Rm | 65.000 | 20.25 | 36.000 | 26.01 | |||||
| Constr. of Parapet | No | 2482.000 | 62.28 | 6.000 | 0.00 | |||||
| Turning point | No | 1.000 | 11.08 | 0.000 | 0.00 | |||||
| Lined Side Drain | Rm | 4280.000 | 65.24 | |||||||
| Total | 1259.55 | 26.01 | 14.34% | |||||||
Page Links: https://pwd.mizoram.gov.in/page/chhingchhip-to-hualtu-roadp
Chhingchhip to Hualtu Road
Department Updates Title
- The Superintending Engineer, PWD, Project Circle, Mizoram on behalf of the Governor of Mizoram, invites Item Rate tender from appropriate class of approved and eligible contractors/firms
- Office Order Dt. 3rd Aug, 2026 Quality Control hnuaia training dilna
- Office order...12/10/26 regarding transfer of JE(Civil)
- Notification Dt. 9th October, 2026 Appointment as Nodal Officer to discuss the priority Sector 'Industrial Corridor & Logistics'.
- Electrician Grade-II Question with Answer Key
Government of Mizoram Latest News