Name of Road : | Constrn. | Chhingchhip- Hualtu Road | ||||||||
(FP) | Date of commencent 18.1.2014 | |||||||||
Package No : | MZ 08-02-7-II(1) | |||||||||
Length of Road : | 24.04 | Phase - VII-Pt II | Period of completetion 24 month | |||||||
Agreement Amount : | 125955771 | Amount in lakhs | ||||||||
Item of Works |
Unit | As per Aggrement | Progress upto the end of last month |
Progress during the month | Cummulative Progress | Remarks | ||||
Phy | Fin | Phy | Fin | Phy | Fin | Phy | Fin | |||
Pavement works | ||||||||||
Repairs of Damages coused by Rain/ spillage of Water | Km | 20.250 | 3.63 | 25.250 | 0.00 | |||||
Constr.of GSB | Km | 20.250 | 303.31 | 11.000 | 0.00 | |||||
Cell Filled Concrete | Km | 20.250 | 757.67 | 0.000 | 0.00 | |||||
Earthern Shoulder | Km | 1126.800 | 36.09 | 0.000 | 0.00 | |||||
Premix carpet | Km | |||||||||
Seal coat | Km | |||||||||
Cell Fill | Km | |||||||||
Earthern Shoulder | Cum | |||||||||
Proctection works | ||||||||||
R/W | Rm | 65.000 | 20.25 | 36.000 | 26.01 | |||||
Constr. of Parapet | No | 2482.000 | 62.28 | 6.000 | 0.00 | |||||
Turning point | No | 1.000 | 11.08 | 0.000 | 0.00 | |||||
Lined Side Drain | Rm | 4280.000 | 65.24 | |||||||
Total | 1259.55 | 26.01 | 14.34% |